The Forestburg Lateral Loop (FBLL) Project consisted of construction of approximately 8.15 km of NPS 10 pipe from the existing NTYL NPS 30 North Lateral Extension Loop 2 and NPS 16 North Lateral Extension, extending East to terminate at the Forestburg East Sales Meter Station inside the ATCO Battle River Generating Plant. This line was constructed to assist in supply of Natural Gas to the coal fired ATCO Battle River Power Generating Station as they convert to a natural gas feed. This 8.15 km line included 4 large HDD crossings, as well as heavy grade and reclamation of a large steep hill within the plant site. This project also included a hot tap into the existing 2 pipelines at the West end of the line and construction of an above ground valve site at this location.