Project Timeline

Construction – November 2016 to March 2017

 

Project Description

The Pipeline Expansion Project consisted of two NPS 24 pipelines of 9.8 and 10.4 km in length. The pipeline traversed multiple crossings, including road, utilities and watercourses. The project included 7 valve sites. The project included two larger HDDs, approximately 400 m and 800 m in length.